PROJECT DETAILS
Case Study: Site Remediation and Civil Works
Site Name:Development Site East Sydney
PROJECT SUMMARY
- Asbestos Abatement – removal of approx. 20,000m2 of AC sheeting;
- Demolition of 10 buildings/site structures – approx. 25,000m2 footprint;
- Demolition of approx. 7,000m2 of concrete hardstand areas;
- Placement and encapsulation of approx. 8,000m3 of lead and PAH impacted soils;
- Construction of onsite containment cell;
Key Project Objectives
- Asbestos abatement, building demolition, excavation and encapsulation of lead impacted soils within onsite containment cell to remove risk of future exposure to general public / on site occupants / workers;
- Remediation of site to ensure protection of local groundwater quality;
- Remediation of site to ensure protection of the surrounding environment, including flora and fauna.
Specialty
Friable Asbestos Soil, Chlorinated Ethene impacted soils, Bulk Excavation, Detailed Civil works, Enclosures